What I need to do to maintain my approval if I modify my equipment during the approval period?

The steps are the same as regular approval, as follows:

Submit the following:

  1. A completed application form (PC-ELEC-App.12). Original signature is required.
  2. Application fee as marked on application form. Make check payable to “The Department of Building and Safety, City of Los Angeles.”
  3. Current product literature (brochure, operational instruction, maintenance manual, owner’s manual).
  4. Photographs or drawings showing the exterior views and internal views of the equipment.
  5. Schematic wiring diagrams. Diagrams should identify the sizes of wires, ratings of fuses, circuit breakers, and other components.
  6. The parts list for the components operating at or above 30 VAC or 24.8 VDC in dry locations or 15 VAC or 12.4 VDC in wet locations. Include the part's function, name of manufacturer, catalog number, electrical ratings, and testing agency component recognition or listing number.
  7. Production sample of the equipment as follows:
    • For General or Laboratory Approval: Submit a current production sample (complete and operable) with all appurtenances to operate the equipment. If the equipment is too heavy or large to ship to the laboratory, arrange for a field location in the City of Los Angeles or at the factory where a complete testing can be performed without on-site restrictions (call the laboratory for a prior arrangement) and pay for the field trip charges.
    • For One-Time Approval of field installed equipment: Provide the field location where the equipment is intended to be installed insuring that it can be evaluated and tested without on-site restrictions. Provide the complete address, phone number, and contact person. Pay for the field trip charges.
  8. For equipment with unlisted transformers, drivers or power supplies with a rating of less than 1KVA, provide two samples with schematic wiring diagrams and specification sheets.

However, the revised approval may require a new model designation of the previous product and the approval would be for the duration that was originally established for the equipment.